Concrete floor slab cost, and what the insulation and screed on top add

A 100mm concrete floor slab costs roughly £54 to £75 per m² for concrete, labour and membrane, or about £84 to £145 per m² with ground preparation, based on MyJobQuote's 2026 figures. That is not a finished floor. Insulation and screed add roughly £40 to £70 per m², so price the whole build-up before comparing quotes.

If you are pricing a concrete floor slab for an extension or a self build, the thing that most often catches budgets out is simple: the slab is only one layer of the floor. A ground floor in a modern home is hardcore, a damp proof membrane, a concrete slab, insulation and a screed, and each layer is often quoted by a different trade. This guide prices the whole build-up so you can compare like with like.

Short answer: using MyJobQuote's September 2026 figures, a 100mm concrete floor slab works out at roughly £54 to £75 per m² for the concrete, the labour and a membrane, or about £84 to £145 per m² once ground preparation is added. The insulation and screed on top add roughly £40 to £70 per m², so a complete ground floor build-up is roughly £125 to £215 per m² before the floor finish.

These are our sums from published averages, not a quote. MyJobQuote notes that costs are likely to be higher in the South East, particularly London, and small floors cost more per m² because fixed costs are spread over less area.

What a concrete floor slab costs per m²

Concrete is sold by the cubic metre and laid by the square metre, which is why slab prices are confusing. A 100mm slab uses 0.1m³ of concrete for every m² of floor, so the concrete itself is a small part of the price. Labour and the ground preparation underneath cost far more.

MyJobQuote's concrete cost guide, updated 17 September 2026, gives these figures:

ItemPublished figurePer m² of a 100mm slab
C20 concrete, standard domestic project£90 to £100 per m³£9 to £10
Average labour rate for laying concrete£40 to £50 per m²£40 to £50
Damp or weed membrane£5 to £15 per m²£5 to £15
Slab subtotal£54 to £75
Ground preparation£30 to £70 per m²£30 to £70
Slab with ground preparation£84 to £145

Swipe the table sideways to see every column.

The same guide lists a sub-base at £30 to £60 per m³, formwork at £10 to £25 per metre, removing existing surfaces at £20 to £50 per m² and skip hire at £120 to £280. Whether those apply depends on your site, so ask each groundworker to show them as separate lines.

At 150mm the C20 concrete is about £13.50 to £15 per m² on the same figures, so a thicker slab specified by an engineer adds only a few pounds per m² in concrete. Any steel mesh or rebar is extra: MyJobQuote notes that reinforcement and the labour to fit it add to the cost, but gives no figure.

A typical ground floor build-up, layer by layer

Approved Document C, the Building Regulations guidance on moisture from the ground, gives a standard way to build a concrete ground supported floor. Many extension floors follow it, with insulation and a screed added on top. trade2base's 2026 Part C guide for trades describes the usual order the same way: compacted hardcore, sand blinding, DPM, then the concrete slab, insulation and screed.

LayerWhat it doesTypical specification
HardcoreFirm, free draining baseWell compacted, no more than 600mm deep
BlindingProtects the membrane from sharp hardcoreA bed that will not damage the sheet
Damp proof membraneStops ground moisturePolyethylene at least 300µm (1200 gauge), sealed joints, linked to the wall DPCs
Concrete slabStructureAt least 100mm, mix ST2 to BS 8500 (ST4 if reinforced), thicker if the structural design requires
InsulationMeets the floor U-valueRigid boards strong enough for the loads above
Slip membrane and edge stripSeparate the screed from insulation and wallsPolythene sheet, foam strip at every wall
ScreedLevel, flat base for the floor finish65mm sand and cement floating, or about 35mm liquid in homes
Floor finishTiles, timber, LVT or carpetLaid once the screed is dry

Swipe the table sideways to see every column.

Approved Document C allows the damp proof membrane above or below the slab. If it goes on top, it must be protected by a screed or floor finish. Where hardcore would be deeper than 600mm, the guidance warns of settlement and cracking and advises a suspended floor slab instead, which is a different build to price. If there is any risk of sulphates in the ground or hardcore, the guidance says the membrane should go at the base of the slab.

For the difference between the slab and the screed, see our guide to screed vs concrete.

Slab costs vs insulation, membrane and screed costs

Short answer: on a typical extension, the layers above the slab cost roughly half as much as the slab and its ground preparation, and they are the part most often missing from an early budget.

LayerPublished 2026 priceSource
Concrete slab, 100mm, with membraneabout £54 to £75 per m²MyJobQuote, September 2026 (our sum)
Ground preparation£30 to £70 per m²MyJobQuote, September 2026
PIR insulation board, material only£7 to £20 per m²MyJobQuote, October 2026
PIR insulation, supplied and fitted, 20m² concrete floor£440 to £800 (£22 to £40 per m²)MyJobQuote, October 2026
Sand and cement screed, supplied and laid£18 to £25 per m²MyJobQuote, August 2026
Liquid screed, supplied and laid£24 to £31 per m²MyJobQuote, August 2026
Floating sand and cement screed, 65 to 75mm£14 to £20 per m²trade2base, June 2026 (excludes VAT, insulation and membranes)
Liquid screed over underfloor heating£20 to £35 per m²trade2base, June 2026 (excludes VAT, insulation and membranes)

Swipe the table sideways to see every column.

Worked example: a 20m² rear extension

Using the figures above for a 20m² floor:

  • Slab with ground preparation: 20m² at £84 to £145 is about £1,680 to £2,900.
  • Insulation, supplied and fitted: £440 to £800, MyJobQuote's own 20m² figure.
  • Screed: £360 to £500 for sand and cement, or £480 to £620 for liquid screed.

That puts the whole floor at roughly £2,480 to £4,320 before the floor finish, against a slab only figure of under £3,000. Skip hire, formwork, steel mesh, and minimum charges on small jobs can all sit on top. Our floor screeding cost guide explains what moves a screed price, and the screed calculator estimates volume for your own floor.

Why the insulation thickness matters to the price

The insulation is set by the Building Regulations, not by preference. Table 4.2 of Approved Document L sets a limiting U-value of 0.18 W/m²K for a new floor in an existing dwelling, which covers most extensions. Note 5 allows the U-value of an extension floor to be calculated using the perimeter and area of the whole enlarged house, which can reduce the insulation needed. Your designer or building control officer confirms the thickness, and that thickness, plus the screed, decides how deep the slab has to sit below the finished floor level.

How thick a concrete floor slab is in a house

Short answer: at least 100mm under Approved Document C, and thicker where a structural engineer specifies it.

The 100mm figure is a minimum for a ground supported floor on well compacted hardcore. Reinforced slabs use the stronger ST4 mix. Garages, poor ground, heavy loads or a slab that also acts as a raft foundation can all call for more, and that is a design decision for the engineer and building control, not the contractor.

The concrete floor thickness people quote online often means the total floor depth, which is a different number. Add the hardcore, the slab, the insulation and the screed, and the build-up from formation level to finished floor is far deeper than the slab alone. That total depth is worth checking early, because it fixes how much the groundworker has to dig out.

Screed depth sits on top. The Mineral Products Association's screed data sheet gives 75mm as the minimum for a floating sand and cement screed over insulation, while noting 65mm is normally considered satisfactory for housing. We lay floating sand and cement screed at 65mm in homes, with about 45mm cover over any underfloor heating pipes. Liquid screed goes down from about 35mm, or about 45 to 50mm over heating pipes to give at least 25mm of cover.

Who does which layer: groundworker, builder, screeder

Short answer: the groundworker or builder digs, lays the hardcore and pours the slab. A screeding contractor such as K & B lays the insulation, membranes and screed.

StageUsually done byNotes
Excavation, hardcore, blindingGroundworker or main builderBuilding control may inspect before the slab
DPM below the slabGroundworker or main builderMust link to the wall DPCs
Concrete slabGroundworker or main builderWe do not pour structural slabs
DPM above the slab, insulation, slip membrane, edge stripScreeding contractor or builderWe install these as part of our work
Underfloor heating pipesHeating installerWe do not install the pipes
ScreedScreeding contractorSand and cement or liquid
Floor finishFlooring fitterOnce the screed tests dry

Swipe the table sideways to see every column.

This split is where gaps appear. A slab quote may include the lower membrane but not the insulation. A builder's price may include insulation but not the screed. Ask every contractor which layers they include, and to what thickness.

When we price the insulation and membranes together with the screed, one team is responsible for the layers above the slab, so the levels and depths are checked against the finished floor level before anything goes down. See our residential screeding page for extensions and new builds, and our liquid screed page if you are choosing a flowing screed.

Practical steps to budget the floor

  1. Fix the finished floor level first. Work down from door thresholds and the existing floor.
  2. Get the insulation thickness confirmed by your designer or building control.
  3. Work out the slab level by subtracting the floor finish, screed and insulation.
  4. Ask the groundworker for a slab price by line: excavation, spoil removal, hardcore, blinding, membrane, concrete, labour.
  5. Ask a screeder to price the layers above the slab as a package.
  6. Allow drying time. Screed needs weeks before most floor finishes go down.

Get a fixed price for your floor

Once the slab is in, or while it is being planned, send us the floor area in m², the finished floor level, the insulation thickness specified, what is going on top (tiles, timber, LVT or carpet), whether there is underfloor heating, and the site postcode. We will price the insulation, membranes and screed as one fixed package, with a written quote within 24 hours.

Send the details through our contact page or call 07466 650936. We call back the same day, and the price we agree before we start is the price you pay.

Sources

FAQs

Frequently asked questions

Is it cheaper to have a screed or to power float the slab?

A power floated slab finished flat enough to take a floor covering saves the screed layer, but it only works where the insulation sits below the slab and the finish tolerances are met. Where the insulation or underfloor heating pipes go above the slab, something has to cover them, which is usually a screed. We do not lay structural power floated slabs.

Can the insulation go under the concrete slab instead?

Yes. Approved Document C allows insulation beneath a slab, provided it is strong enough to carry the slab and floor loads, and boards below the membrane should have low water absorption. The screed then goes directly on the slab, bonded or unbonded, so the layers above the slab change and so does the price.

Do I need building control for a new concrete floor?

For an extension, almost always, because the floor has to meet the moisture rules in Approved Document C and the U-value in Approved Document L. Speak to your local authority building control team or a registered building control approver before work starts.

How long after the slab is poured can the screed go down?

It depends on the programme and the specification, so follow your engineer and screed manufacturer. Insulation and a floating screed are laid onto the cured slab with a membrane between them. The longer wait is the screed itself: sand and cement and calcium sulphate screeds dry at about a day per millimetre for the first 40mm, then more slowly.

Why do slab quotes vary so much?

Mainly because of what is under and around the slab. Excavation depth, spoil removal, access for the concrete lorry or pump, formwork and the amount of hardcore change from site to site. Ask each contractor to price the same specification line by line so the figures are comparable.

Our services

Services mentioned in this article

Fresh floor screed laid against a blue perimeter edge strip in a new build

Insulation & Membranes

Insulation boards, damp proof and slip membranes, edge strip and acoustic layers installed correctly under the screed, so every layer works together.

Finished floor screed in a large glazed room

Residential Screeding

Screeding for home extensions, renovations, loft and garage conversions, basements and self builds, with honest advice and a clean, tidy job.

Power floating a floor screed to a smooth finish

Sand & Cement Screed

The proven, versatile choice. Traditional sand and cement screed is mixed on site, compacted by hand and finished to a level, durable base for any floor covering.