info@kandbscreeding.co.uk

Choosing a screed

Waterproof self levelling compound: what to use in bathrooms and wet rooms

There is no waterproof self levelling compound in the sense most people mean. Levelling compounds and screeds give a flat, sound base and cope with the odd splash, but they are not a waterproof barrier. In a shower or wet room the water is kept out by a tanking system laid over the screed, and the floor falls are formed in the screed or a former first.

Finished floor screed in a plain walled room

Search for a waterproof self levelling compound and you will find plenty of products described as suitable for bathrooms. That is not the same as waterproof. A levelling compound makes a floor flat; it does not stop water reaching the screed, the slab or the ceiling below.

Short answer: self levelling compound is, at most, water resistant. It is not waterproof. In a bathroom it is a smoothing layer under the tiles or vinyl. In a shower area or wet room, waterproofing comes from a separate tanking kit, tanking mat or waterproof backer board, laid over a base that already has the falls built in.

The figures below come from The Tile Association's Tiling Guide, ARDEX UK product pages and Impey wet room installation guides. Where your own product data sheet says something different, follow the data sheet.

Is self levelling compound waterproof?

No. A self levelling compound is a cement based (or calcium sulphate based) powder mixed with water or a latex liquid and poured a few millimetres thick to smooth a floor. Once cured it is hard and will not dissolve if it gets wet, which is why it is fine under bathroom flooring. But it is porous, it can crack if the base moves, and water that gets through tile joints or around a waste will travel into and under it.

Look at the data sheets and the language is consistent. ARDEX K 15, a widely used smoothing compound, is described by its strength and speed: laid from feather edge to 35mm, walkable after 2 hours and ready for floorcoverings in as little as 4 hours. Nothing on the page claims it waterproofs a floor. The products ARDEX does sell for that job sit in a separate waterproofing range.

Outdoor surfaces are a different case again. There, only a compound sold for external use will do, as our guide to exterior self levelling compound explains.

The Tile Association is just as clear from the other side: in wet rooms and showers "it is essential to tile onto a waterproof background", and without proper waterproofing, water getting behind the tiles "can cause serious damage".

Water resistant vs waterproof: what each layer does

Every layer in a tiled wet room floor has one job. Problems start when one layer is expected to do another's.

LayerIts jobWaterproof?
Concrete slab or timber deckStructureNo
Screed (sand and cement)Level, falls to the drain, solid baseNo, but tolerates damp well
Levelling compoundSmooth, flat surface, a few mm thickNo
PrimerHelps the tanking bondNo
Tanking kit, mat or backer boardKeeps water out of everything belowYes
C2 tile adhesive, solid bedHolds the tilesWater resistant
Tiles and groutWearing surfaceNot reliably, grout is porous

Swipe the table sideways to see every column.

The Tile Association lists three ways to make the background waterproof:

  1. A tanking kit, usually a water based liquid applied membrane, a self adhesive flexible sealing strip and primer.
  2. A waterproof tanking mat.
  3. Waterproof tile backer board.

It also says to use at least a C2 adhesive, to solid bed the tiles on walls and floors, and to take care that every joint and corner is taped without creases.

For heavier duty areas there are tougher membranes. ARDEX WPM 200, for example, is a solvent free epoxy liquid membrane listed for wet areas and tanking for tiling, applied to concrete, screed and render. It is overcoated between 8 and 24 hours at 20°C. That is a tanking product; a levelling compound is not.

Wet room floors: falls in the screed, then tanking

A walk in shower or wet room floor has to fall towards the drain so water does not sit on the tiles. The order matters:

  1. Form the falls. Either lay a screed shaped to fall to the gully or linear drain, or fit a pre formed wet room former that has the gradient built in.
  2. Let it dry. Impey's linear drain guide says to "always allow new screeds to fully dry before applying the final finish of waterproofing and tiles".
  3. Prime and tank. Apply the tanking system over the whole floor and up the walls as its manufacturer specifies, with the tape or corner pieces at every joint and around the drain. Impey's WaterGuard membrane guide, for example, says to prime all porous surfaces and only begin tanking "when primer is fully dry".
  4. Tile to follow the falls. The same Impey guide states that "in all cases the tiles must be laid to follow the falls/gradient" of the former.

Why self levelling compound cannot form the falls

A self levelling compound does exactly what its name says: it flows until it is flat. Pour it into a shower area and it flows out flat, so it cannot hold a slope to the drain, which is the opposite of what you need. Falls are formed with a semi dry sand and cement screed, which is ruled off to a slope by hand, or with a manufactured former.

The exact gradient depends on the drain and former. Follow the drain or former manufacturer. Impey's linear drain guide points installers to BS 8204 and BS 5385-3 for further guidance.

Where levelling compound does belong in a bathroom

Compound is useful in bathrooms that are not wet rooms: a room with a raised shower tray or a bath, finished in LVT, vinyl or tiles. It takes out small dips and trowel marks so the finish sits flat. Prime first; see our screed primer guide. Our floor levelling work typically uses compound from about 2mm to around 10mm over a sound screed or slab, aiming at SR1, no more than 3mm under a 2m straightedge (the BS 8204 surface regularity classes). If a floor needs more than that, a screed is usually the better fix, because deep pours of compound to correct a bad floor can crack and debond.

In a wet room, compound can smooth a base before tanking only if the tanking manufacturer accepts it as a substrate. Check that before you pour.

Which screeds suit bathrooms, and why anhydrite needs care

The screed under a bathroom floor should be one that copes if a leak ever gets through.

Screed typeIn a bathroomIn a wet room or level shower
Sand and cementSuitableOur usual choice: can be laid to falls by hand
Cement based flowing screedSuitableOnly as a flat base: it self levels, so falls need a former or a separate fall screed
Calcium sulphate (anhydrite)Usable with care and tankingAvoid where it will be permanently wet
Levelling compoundAs a smoothing layer onlyNot for falls, not waterproof

Swipe the table sideways to see every column.

Calcium sulphate screed is excellent over underfloor heating, but it is gypsum based. The Tile Association warns of two problems when tiling onto it: a weak surface laitance that must be removed, and ettringite, formed when cement based adhesive reacts with the gypsum, which can debond tiles. It must also dry properly: the guide suggests about 1 day per mm up to 40mm, then 2 days per mm beyond that, to reach no more than 1% moisture or 75% relative humidity. Screed and adhesive makers can be stricter: for its standard screeds, Gyvlon's post installation guidance sets 0.5% for ceramic or porcelain tiles fixed with a primer and cementitious tile adhesive, and allows 1.0% only with a primer and calcium sulphate tile adhesive, so work to the limit for the adhesive your tiler uses. Our anhydrite screed guide covers preparation in detail. For a wet room, sand and cement is usually the safer base.

Sand and cement screed suits wet areas because cement is not weakened by moisture the way gypsum is, it does not react with cement based adhesives the way a gypsum screed can, and it can be shaped to falls. It still needs the primer the tanking or adhesive maker specifies. On our figures, a floating sand and cement screed is about 65mm in a home, and a bonded screed 25 to 40mm. Because a fall screed is shaped to slope, it is thinnest at the drain and thicker at the far side, so the depth has to be planned from the drain outwards.

How to fit a shower tray or wet room former on a concrete floor

To fit a shower tray on a concrete floor, check the slab is level, then either set a raised tray on its legs or a mortar bed, or recess a wet room former into the slab and bed it as the maker's guide says. A wet room floor must then be tanked before it is tiled. Most bathroom refits are on an existing concrete floor. There are three common routes:

  • Raised shower tray. The tray sits on its own legs or a mortar bed, the waste runs above the slab, and the floor around it only needs to be flat. A thin levelling compound is often enough.
  • Level access former. A wet room former is recessed into the slab so it finishes flush. Impey's EasyFit guide for concrete floors says to check the floor is level first, excavate the area to at least 35mm, remove enough concrete for the waste and trap, bed the former on a mix and screw it down. It also says a tanking membrane must be applied when the floor is tiled.
  • Screed laid to falls. The whole floor, or the shower zone, is screeded to fall to a gully or linear drain. This suits larger wet rooms and odd shapes.

Breaking into a slab to run a waste can disturb the damp proof membrane in a ground floor. If you cut into the slab, the membrane has to be made good before the screed goes back. If the existing screed is cracked or hollow, it is better to replace that section first; see our screed repairs service.

Drying before tanking and tiles

Tanking a damp screed traps the moisture. On our figures, screed dries at roughly 1 day per mm for the first 40mm and slower after that, and the floor should be tested with a hygrometer to about 75% RH before the finish goes down. A fall screed in a small room is thin at the drain and thicker at the walls, so test the thick side. Our guide to screeding before flooring explains the testing and preparation steps.

What a bathroom screed costs

Published UK figures from MyJobQuote (updated August 2026) put installed sand and cement screed at £18 to £25 per m², fast drying screed at £20 to £28 per m² and flowing screed at £24 to £31 per m². Those rates are based on a 20m² room. Bathrooms are smaller and involve falls, drains and cutting in, so ask for a total price for the job rather than multiplying a per m² rate. Our floor screeding cost guide breaks the figures down further.

Get a fixed price for your floor

Send us the bathroom size in m², the shower layout (raised tray, level access former or full wet room, and where the drain sits), what the floor is now (concrete, existing screed or timber) and the finish you plan to use, plus your postcode. Photos help. We will price a screed laid to falls, ready for your tanking system, or a levelling coat if that is all the floor needs.

You get a same day call back and a written quote within 24 hours, with a fixed price agreed before work starts. Contact us here or call 07466 650936.

Sources

FAQs

Frequently asked questions

Can I just paint tanking straight onto old tiles?

Only if that tanking system's manufacturer says its product can go over existing tiles, and on what preparation. Check the data sheet before you start. Loose or hollow tiles must come up first, because any movement under the membrane can split it. If the floor also needs falls adding, the old tiles normally come up so the screed or former can go in.

Is waterproof grout enough for a shower floor?

No. Cement grout is porous, and even epoxy grout only protects the joints, not the adhesive bed or the screed. Water still reaches the base through hairline cracks, around the drain and at the wall junction. The Tile Association guidance is to tile onto a waterproof background in showers and wet rooms, so the tanking does the waterproofing and the grout simply fills the joints.

Can a wet room go on a first floor timber floor?

Yes, but it is a different build. Formers made for timber floors sit between or on the joists, the deck must be stiff, and The Tile Association does not recommend plywood or timber as a direct tiling background in wet areas. Get the joists and deck checked before choosing a former. For levelling the deck itself, see levelling compound for wooden floors.

How long after screeding can a wet room be tanked?

Only once the screed is dry enough for the tanking product, which its data sheet will state. Test before you tank, not after. A thin bonded fall screed dries far sooner than a deep floating screed. Plan the programme around a moisture test, not a fixed number of days.

Does a bathroom with a normal shower tray need tanking on the floor?

Not always. If a raised tray with a sealed upstand takes all the water, the rest of the floor sees splashes only, and a water resistant finish on a sound, level base is common. Tanking the walls inside the shower is still good practice. Level access showers and wet rooms are different: the whole floor around the drain needs tanking.

Our services

Services mentioned in this article

Power floating a floor screed to a smooth finish

Sand & Cement Screed

The proven, versatile choice. Traditional sand and cement screed is mixed on site, compacted by hand and finished to a level, durable base for any floor covering.

Finished screed floor in a new build room

Floor Levelling

Self levelling compounds and subfloor levelling that turn an uneven screed or slab into a smooth, flat base for LVT, vinyl, tiles and engineered wood.

Corridor mid screed with timber formwork and edge detailing

Screed Repairs

Cracked, hollow, crumbling or uneven screed repaired properly, from local patch repairs to breaking out and relaying whole floors.

Free, no-obligation quote

Ready to get your floors done properly?

Leave a request and we will call you back the same day. Your quotation will be ready within 24 hours, with no hidden fees and no obligation.